1- Mechanism for the competent authority to issue any decision that contributes to increasing costs on the industrial establishment:
This mechanism aims to enable the Ministry to measure the impact on the industrial establishment's ability to respond to decisions issued by the competent authority that may contribute to increasing costs (direct and indirect) on the industrial establishment, and the effect of that on the industrial sector, as follows:
- The competent authority shall provide the Ministry with the draft decision, specifying: the objective, justifications, direct and indirect costs on the industrial establishment, accompanied by supporting documents.
- The Ministry shall study the draft decision within a period not exceeding (10) working days from the date the competent authority provides the Ministry with the draft decision.
- The Ministry shall send its observations regarding the draft decision to be applied to the industrial establishment to the competent authority within the aforementioned period, clarifying an assessment of the effects that may result from its application on the industrial establishment.
2- Mechanism for fining the industrial establishment by the competent authority:
This mechanism aims to inform the Ministry of the data related to the fined industrial establishment and analyze its status in coordination with the competent authority; to ensure the industrial establishment's compliance with the relevant procedures and instructions, and to measure the impact resulting on it and on the industrial sector due to the fine imposed for the violation, as follows:
- After detecting the violation that requires fining and imposing the fine - according to the relevant regulatory procedures - the competent authority shall notify the Ministry of the name of the industrial establishment, the type of violation, and the corrective period granted to the industrial establishment, if legally applicable.
- The Ministry shall coordinate with the industrial establishment to correct the violation, according to the relevant regulatory procedures.
This paragraph does not apply to matters within the jurisdiction of the relevant administrative or quasi-judicial committees.
3- Mechanism for the competent authority to close production lines of the industrial establishment:
This mechanism aims to inform the Ministry of the data related to the violating industrial establishment and analyze its status and history in coordination with the competent authority; to ensure the industrial establishment's compliance with the relevant procedures and instructions, and to verify and measure the impact resulting on it and on the industrial sector due to the competent authority closing the production lines of the industrial establishment, as follows:
- In case a production line is stopped due to committing a violation that legally requires such action, the competent authority shall provide the Ministry with a detailed report on the reasons for the stoppage, attaching the related documents, within a period not exceeding (5) working days from the date of stopping the production line.
- The Ministry shall coordinate with the industrial establishment to correct the violation, according to the relevant regulatory procedures.
- The Ministry shall analyze the regulatory procedures taken by the competent authority regarding the closure of the industrial establishment's production line, measure its impact on the development of the industry and the targets of Saudi Arabia's Vision 2030, and provide the competent authority with these findings.
This paragraph does not apply to matters within the jurisdiction of the relevant administrative or quasi-judicial committees.
4- Mechanism for the competent authorities to close the industrial establishment:
This mechanism aims to inform the Ministry of the reasons that led to the closure of the industrial establishment, and to verify and measure the impact resulting on it and on the industrial sector due to the closure decision, as follows:
- After detecting the violation that requires closing the industrial establishment or the industrial establishment with a single production line - temporarily or permanently - according to the relevant regulatory procedures; the competent authority shall provide the Ministry with a report on the reasons for closing the industrial establishment or factory, and corrective procedures to stop the implementation of the closure - if any - attaching the related documents, within a period not exceeding (15) working days from the date of detecting the violation.
- The Ministry shall coordinate with the industrial establishment or the industrial establishment with a single production line to correct the violation, according to the relevant regulatory procedures.
- The Ministry shall analyze the regulatory procedures taken by the competent authority regarding the closure of the industrial establishment or the industrial establishment with a single production line, measure its impact on the development of the industry and the targets of Saudi Arabia's Vision 2030, and provide the competent authority with these findings.
This paragraph does not apply to matters within the jurisdiction of the relevant administrative or quasi-judicial committees.